Salco-Logo-Red-No-Bg

MacKimmie Library UoC

Date of Project: 2017

Brief Summary: Over the course of 12 months, Salco undertook the task of removing all architectural components from an 8-story building located at the University of Calgary. Utilizing a mast scaffold and a stationary crane, the entire envelope of the building was meticulously removed. In addition, due to unsuitable soils, shoring of the basement walls was required. Salco efficiently managed a crew of 20 workers throughout the project. 

Related projects